The scope of the project included a number of modernizations and improvements including site work, a new kitchen and minor cafeteria renovations including the addition of a stage, a security vestibule addition, bathroom renovations, a gym roof replacements, and main entry accessibility improvements.
Judson ISD
Garza Bomberger & Associates
Design-Bid-Build
November 2021
10,000
$4,260,000
The cafeteria renovations included the addition of a stage, re- worked queue lines, and expanded kitchen to increase efficiency and better serve the students. The cafeteria received cosmetic updates as well. The admin area, and in particular, the main entry received cosmetic updates as well as the addition of a security lobby with ADA improvements. The project healed part of an old building and gave new life to the campus.