MacArthur High School Fine Arts Addition & Renovation

CLIENT:

North East Independent School District

COST:

$8,925,000

SIZE:

28,779 sq. ft.

COMPLETION DATE:

October 31, 2019

DELIVERY METHOD:

Construction Manager at Risk

ARCHITECT:

Lopez Salas

AWARDS RECEIVED:

Project Description: This is a CM at Risk project with a 5-month pre-construction timeline and a 17-month phased construction schedule. The MacArthur project includes partial demolition of the existing fine arts building and construction of a new 2-story suspended slab fine arts facility addition tied into the existing structure on both floors. The new facility will include new orchestra and dance facilities, renovations to the existing band and drama areas on both floors including a new dance studio mezzanine, installation of a new large-capacity freight elevator, multiple new restroom facilities on both floors as well as various site improvements including parking, landscape, irrigation, drainage, site utilities, and hardscape. The challenges of this project are there location of the existing main communication raceways currently underground in the footprint of the new facility and the separation of the existing occupied building structure we are adding onto with a 1” expansion joint between the operating interior corridors and the new structure. Our firm specializes in complex renovations and our staff excels at strategically planning and phasing the projects for no incidents or disruptions to the campus during every stage of the project.

Square Footage:  28,779 (17,039 SF Addition;11,740 SF Renovation)

Project Location:  2923 MacArthur View, San Antonio, TX 78217

Owner Contact:  Gary Sullivan 210-407-0438

No items found.

-MORE PROJECTS-

10609 IH-10 West, Suite 200
San Antonio, TX 78230

- CONTACT US -

HOW CAN MARKSMEN GENERAL CONTRACTORS SERVE YOUR CONSTRUCTION NEEDS?
Thank you! We look forward to working with you!
Oops! Please make sure you filled out each section of the form.